Kenaston project both pricey and risky

Advertisement

Advertise with us

This week, newly re-elected Winnipeg Mayor Scott Gillingham said that one of the most significant projects he plans to push forward during his current administration is the major road project to widen Kenaston Boulevard and build in a series of improvements to everything from bridges to transit to sewer systems.

Read this article for free:


By clicking the button above, an account will be created and you will begin to receive some of our recommended newsletters. You may opt out of any newsletter by visiting your Email and Communication Preferences page or by clicking "unsubscribe" at the bottom of any email.

or

Already have an account? Log in here »

To continue reading, please subscribe:

Digital Subscription

One year of digital access for only $1.44 a week*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles

*Billed as $5.77 plus GST every four weeks. After 52 weeks, price increases to the regular rate of $19.95 plus GST every four weeks. Offer available to new and qualified returning subscribers only. Cancel any time.

To continue reading, please subscribe:

Add Free Press access to your Brandon Sun subscription for only an additional

$1 for the first 4 weeks*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles
Start now

*Your next Brandon Sun subscription payment will increase by $1.00 and you will be charged $17.95 plus GST for four weeks. After four weeks, your payment will increase to $24.95 plus GST every four weeks.

Opinion

This week, newly re-elected Winnipeg Mayor Scott Gillingham said that one of the most significant projects he plans to push forward during his current administration is the major road project to widen Kenaston Boulevard and build in a series of improvements to everything from bridges to transit to sewer systems.

It’s expensive. Free Press columnist Brent Bellamy pointed out in 2023 that the project’s costs had “risen steadily from $129 million in 2009, to $375 million in 2015 and $450 million in 2018.”

During that time, details of the project may have changed — heck, the whole scope of the project might have expanded, dragging in new elements along the way — but what is clear is that the only direction the project’s costs have gone is up.

Brent Bellamy photo
                                Traffic on Kenaston/Route 90

Brent Bellamy photo

Traffic on Kenaston/Route 90

By 2019, the city was ballparking $500 million as the construction cost.

A 2023 Class 3 cost estimate for the project — meaning that costs were considered accurate within plus or minus 20 to 30 per cent — came in at $736.7 million in combined construction and financing costs.

(It’s worth pointing out that the city’s 2019 Class 3 estimate for the fiscally challenged North End sewage treatment plant was $1.8 billion, while the current cost of the project is estimated to be $3.1 billion — well over the proposed 30 per cent maximum variance.)

The Kenaston project’s numbers have already grown since 2023, reaching $757 million in combined construction and financing costs. The current estimate for the construction costs of the project have risen to $613.9 million, accompanied by financing costs of $143.4 million.

That steady increase alone should give us some pause.

But let’s look at some other numbers.

The cumulative increase in inflation in Canada since 2009 has been 44.54 per cent.

The cumulative rise in the cost of the Kenaston project is much, much more.

Compared with the $129 million estimate in 2009, the cost of the project has risen more than fourfold.

Even compared to the probably more reasonable 2015 estimate of $375 million, the cost has risen by 64 per cent, while inflation has grown by 33.75 per cent since 2015.

We get it: costs rise. And apparently, construction numbers for city projects rise even more.

But there is a point at which numbers just don’t make much sense any more: they rattle around in your head as you try to grasp their concept.

The project is not without clear merits: decoupling storm sewers and sanitary sewers is a pollution-control measure that has to be undertaken, even if that part of the Kenaston project is not going to even put a dent in the issue for most of Winnipeg.

Likewise, there is merit to improving traffic flows, even if that means enabling Winnipeg’s suburban sprawl to continue. Improvements to active transportation systems and transit flows are also valuable — but at what cost?

It’s fair to say that part of the equation is still dangling in the fiscal wind.

The City of Winnipeg has just played a successful game of chicken with the largest infrastructure project in the city’s history: threatening Winnipeg taxpayers with massive water and sewer increases seems to have successfully brought federal and provincial commitments of a combined $1 billion to meet massive cost overruns and finish the North End sewage treatment project.

And the city has been clear in its view that it wants federal and provincial involvement in the current Kenaston project — but that’s not without risks. The two higher levels of government haven’t yet said they will play ball.

So risk there is aplenty.