Winnipeg water plant repairs expected to cost more, take longer
Advertisement
Read this article for free:
or
Already have an account? Log in here »
To continue reading, please subscribe:
Digital Subscription
One year of digital access for only $1.44 a week*
- Enjoy unlimited reading on winnipegfreepress.com
- Read the E-Edition, our digital replica newspaper
- Access News Break, our award-winning app
- Play interactive puzzles
*Billed as $5.77 plus GST every four weeks. After 52 weeks, price increases to the regular rate of $19.95 plus GST every four weeks. Offer available to new and qualified returning subscribers only. Cancel any time.
To continue reading, please subscribe:
Add Free Press access to your Brandon Sun subscription for only an additional
$1 for the first 4 weeks*
- Enjoy unlimited reading on winnipegfreepress.com
- Read the E-Edition, our digital replica newspaper
- Access News Break, our award-winning app
- Play interactive puzzles
*Your next Brandon Sun subscription payment will increase by $1.00 and you will be charged $17.95 plus GST for four weeks. After four weeks, your payment will increase to $24.95 plus GST every four weeks.
Read unlimited articles for free today:
or
Already have an account? Log in here »
The final repairs to Winnipeg’s drinking water treatment plant are expected to cost an additional $2 million and begin several months later than planned.
In January, water and waste officials estimated repairs to address alleged construction deficiencies at the plant, which opened in 2009, would cost about $38 million more in the coming years. That would add to $8.8 million the city previously spent to repair the plant.
The first phase of work to improve the surface of concrete tanks, a key final repair project, was slated to begin at the end of 2026 and take about 4 1/2 years to complete.
KEN GIGLIOTTI / FREE PRESS FILES
The Winnipeg drinking water treatment plant at Deacon reservoir in the RM of Springfield.
A new report states that concrete construction is now expected to start in the fall of 2027, with a combined cost for three phases of work reaching about $40.2 million, up from the previous $38 million.
Initial estimates are now based on more refined designs, which drove up the expected price for the first phase of work from $17.2 million to $19.5 million, said Winnipeg water and waste director Tim Shanks.
“We’re really close, we’re going to tender it in early 2027. We’re that much more confident in the price (now),” said Shanks.
Construction will be delayed several months to complete design changes that will ensure all new equipment is compatible.
“There’s a system at the bottom of the filters that (has) a bunch of little pipes and fittings that let the filter drain. We have to redesign those,” said Shanks.
Four of six deficiencies at the plant have already been resolved and the problems have never affected the quality of drinking water, he said.
“None of this stuff has ever jeopardized operation of the plant.”
The city also completed a design for a new sodium hypochlorite generating system at the plant, the only other remaining alleged construction deficiency.
That study determined the system would cost $7.4 million. Once maintenance, labour and operating effects were factored in, the city decided it is better off continuing to buy the chemical in bulk instead.
“Essentially, it was the same cost between the two options. There are operational considerations that make it more attractive to continue doing what we’re doing now,” said Shanks.
The first phase of concrete repairs will likely be completed around 2031, while subsequent phases are expected to continue through “most of the 2030s,” said Shanks.
The extended timeline is largely due to the need to do small pieces of each project at a time to avoid any interruption in drinking water treatment, he said.
“You can’t take the whole treatment plant out of service and replace all the concrete … We have to work around different shutdowns,” said Shanks.
By 2012, the $300-million Deacon water treatment plant suffered from a leaky roof and some equipment had failed and/or exploded, a city legal statement claims.
The city filed a lawsuit in 2015 against multiple builders over alleged construction deficiencies at the plant. Those allegations were never tested in court, however, because the city missed a legal deadline to move the case forward.
joyanne.pursaga@winnipegfreepress.com
X: @joyanne_pursaga
Born and raised in Winnipeg, Joyanne loves to tell the stories of this city, especially when politics is involved. Joyanne became the city hall reporter for the Winnipeg Free Press in early 2020.
Our newsroom depends on a growing audience of readers to power our journalism. If you are not a paid reader, please consider becoming a subscriber.
Our newsroom depends on its audience of readers to power our journalism. Thank you for your support.