A timeline of the controversial Keystone XL pipeline project:

Advertisement

Advertise with us

July 2008: TC Energy Corp. — then called TransCanada Corp. — and ConocoPhillips, joint owners of the Keystone Pipeline, propose a major extension to the network. The expansion, dubbed Keystone XL, would carry hundreds of thousands of barrels of oilsands bitumen from Alberta to Texas.

Read this article for free:


or

Already have an account? Log in here »

To continue reading, please subscribe:

Subscribe and receive a limited-edition Free Press branded hat or tote.

Digital Subscription

One year of digital access for only $205*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles

*First annual payment billed as $205.00 + GST for one year. This annual subscription will automatically renew at $233.00 + GST every 52 weeks (10% off the regular annual price of $259.35). Offer available to new and qualified returning subscribers only. Cancel any time.

To continue reading, please subscribe:

Add Free Press access to your Brandon Sun subscription for only an additional

$1 for the first 4 weeks*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles
Start now

*Your next Brandon Sun subscription payment will increase by $1.00 and you will be charged $17.95 plus GST for four weeks. After four weeks, your payment will increase to $24.95 plus GST every four weeks.

Hey there, time traveller!
This article was published 18/01/2021 (2089 days ago), so information in it may no longer be current.

July 2008: TC Energy Corp. — then called TransCanada Corp. — and ConocoPhillips, joint owners of the Keystone Pipeline, propose a major extension to the network. The expansion, dubbed Keystone XL, would carry hundreds of thousands of barrels of oilsands bitumen from Alberta to Texas.

2009: As the U.S. State Department wades through comments based on an environmental assessment of the project, TransCanada starts visiting landowners potentially affected by the pipeline. Opposition emerges in Nebraska.

June 2009: TransCanada announces it will buy ConocoPhillips’s stake in Keystone.

March 2010: The National Energy Board approves TransCanada’s application for Keystone XL, though the OK comes with 22 conditions regarding safety, environmental protection and landowner rights.

April 2010: The U.S. State Department releases a draft environmental impact statement saying Keystone XL would have a limited effect on the environment.

June-July 2010: Opposition to Keystone XL begins mounting in the United States. Legislators write to then-secretary of state Hillary Clinton calling for greater environmental oversight; scientists begin speaking out against the project; and the Environmental Protection Agency questions the need for the pipeline extension.

July 2010: The State Department extends its review of Keystone, saying federal agencies need more time to weigh in before a final environmental impact assessment can be released.

March 2011: The State Department announces a further delay in its environmental assessment.

Aug. 26, 2011: The State Department releases its final environmental assessment, which reiterates that the pipeline would have a limited environmental impact.

August-September 2011: Protesters stage a two-week campaign of civil disobedience at the White House to speak out against Keystone XL. Police arrest approximately 1,000 people, including actors Margot Kidder and Daryl Hannah as well as Canadian activist Naomi Klein.

Sept. 26, 2011: At a demonstration on Parliament Hill, police arrest 117 of 400 protesters.

Nov. 10, 2011: The State Department says TransCanada must reroute Keystone XL to avoid an ecologically sensitive region of Nebraska.

Nov. 14, 2011: TransCanada agrees to reroute the line.

December 2011: U.S. legislators pass a bill with a provision saying President Barack Obama must make a decision on the pipeline’s future in the next 60 days.

Jan. 18, 2012: Obama rejects Keystone, saying the timeline imposed by the December bill did not leave enough time to review the new route. Obama said TransCanada was free to submit another application.

Feb. 27, 2012: TransCanada says it will build the southern leg of Keystone XL, from Cushing, Okla., to the Gulf Coast, as a separate project with a price tag of $2.3 billion. This is not subject to presidential permission, since it did not cross an international border.

April 18, 2012: TransCanada submits a new route to officials in Nebraska for approval.

May 4, 2012: TransCanada files a new application with the State Department for the northern part of Keystone XL.

Jan. 22, 2013: Nebraska Gov. Dave Heineman approves TransCanada’s proposed new route for Keystone XL, sending the project back to the State Department for review.

January 2013: Pipeline opponents file a lawsuit against the Nebraska government claiming the state law used to review the new route is unconstitutional.

Jan. 31, 2014: The State Department says in a report that Keystone XL would produce fewer greenhouse gas emissions than transporting oil to the Gulf of Mexico by rail.

Feb. 19, 2014: A Nebraska judge rules that the law that allowed the governor to approve Keystone XL over the objections of landowners was unconstitutional. Nebraska said it would appeal.

April 18, 2014: The State Department suspends the regulatory process indefinitely, citing uncertainty about the court case in Nebraska.

Nov. 4, 2014: TransCanada says the costs of Keystone XL have grown to US$8 billion from US$5.4 billion.

November-December 2014: Midterm elections turn control of the U.S. Congress over to Republicans, who say they’ll make acceptance of Keystone XL a top priority. But Obama adopts an increasingly negative tone.

Jan. 9, 2015: At the Nebraska Supreme Court, by the narrowest of margins, a panel of seven judges strikes down the lower-court decision.

Jan. 29, 2015: The U.S. Senate approves a bill to build Keystone XL, but the White House says Obama would veto it.

Feb. 24, 2015: Obama vetoes the bill.

June 30, 2015: TransCanada writes to then-secretary of state John Kerry and other U.S. officials saying the State Department should include recent climate change policy announcements by the Alberta and federal governments in its review of Keystone XL.

Nov. 2, 2015: TransCanada asks the U.S. government to temporarily suspend its application.

Nov. 4, 2015: The U.S. government rejects that request.

Nov. 6, 2015: The Obama administration rejects TransCanada’s application to build the Keystone XL pipeline. TransCanada CEO Russ Girling says he is disappointed, but continues to believe the project is in the best interests of both Canada and the U.S.

Jan. 6, 2016: TransCanada files notice to launch a claim under Chapter 11 of the North American Free Trade Agreement, alleging the U.S. government breached its legal commitments under NAFTA. The company also files a lawsuit in U.S. Federal Court in Texas arguing that Obama exceeded his powers by denying construction of the project.

May 26, 2016: Republican presidential contender Donald Trump says he would approve Keystone XL if elected, a pledge he repeats several times during the campaign.

Nov. 8, 2016: Trump is elected president.

Jan. 24, 2017: Trump signs an executive order that he says approves Keystone XL, but suggests the United States intends to renegotiate the terms of the project. He also signs an order requiring American pipelines to be built with U.S. steel.

Nov. 9, 2018: A U.S. federal judge blocks the pipeline’s construction to allow more time to study the potential environmental impact.

March 29, 2019: Trump issues a new presidential permit in an effort to speed up development of the pipeline

May 3, 2019: TransCanada changes its name to TC Energy.

March 31, 2020: Alberta agrees to invest $1.5 billion in Keystone XL, followed by a $6 billion loan guarantee in 2021.

April 7, 2020: Construction begins, despite calls from Indigenous groups and environmentalists to pause their efforts.

May 18, 2020: Joe Biden, then the presumptive Democratic presidential nominee, vows to scrap Keystone XL if elected, but doesn’t set out a timeline for doing so.

Nov. 3, 2020: Biden is elected president.

Jan. 17, 2021: Transition documents show Biden plans to cancel Keystone XL on the first day of his presidency.

This report by The Canadian Press was first published Jan. 18, 2021.

Companies in this story: (TSX: TRP)

Report Error Submit a Tip

More Stories

Purple Noodle serves up interesting mix of Asian dishes

Alison Gillmor 4 minute read Preview

Purple Noodle serves up interesting mix of Asian dishes

Alison Gillmor 4 minute read Wednesday, Sep. 4, 2019

With a bright atmosphere and fresh flavours, this new Asian noodle house offers lots of range (with Japanese, Chinese and Vietnamese inflections), but not always the deep-down authenticity you might get at more specialized restos.

Tucked into Stafford Square at the corner of Stafford Street and Pembina Highway and open from lunch until late, the Purple Noodle Bar is a small venue located down a flight of stairs. It’s a basement room that doesn’t feel like a basement room, with clean, mod decor and lots of light.

The eclectic menu offers Asian snacks, as well as pho, ramen and wonton soups, and vermicelli and rice dishes. There are a few vegetarian and vegan options, along with some gluten-friendly dishes.

The agedashi tofu is tender with a gingery finish to the sauce, but the coating lacks crispness.

Read
Wednesday, Sep. 4, 2019

Fantastical, moving graphic memoir explores addictions, organ procurement and more

Reviewed by Candida Rifkind 4 minute read Preview

Fantastical, moving graphic memoir explores addictions, organ procurement and more

Reviewed by Candida Rifkind 4 minute read Saturday, May. 30, 2026

At the heart of Mary Shelley’s 1818 classic Frankenstein and its many pop culture adaptations is the scene in the mad scientist’s lab where Victor Frankenstein, helped by a bolt of lightning, animates the grotesque figure made out of human and animal parts lying on his anatomy table.

As much as Shelley’s novel is a philosophical investigation into the desire of modern science to create new life, it is also a gruesome window into the clandestine European trade in graveyard and battlefield body snatching that fuelled early 19th-century anatomy research, medical training and public dissection theatres.

Whose bodies ended up on the slab to advance medical knowledge? As Montreal-based artist Arizona O’Neill explains in her captivating first graphic narrative, it was inevitably poor, racialized and criminalized bodies that were deemed appropriate for the indignities of public display and dissection in earlier periods.

But what about today? This is the central question driving the story of Opioids & Organs, O’Neill’s beautifully drawn story of coming to terms with her father’s untimely death due to a fentanyl overdose as well as the awful truth that Canada’s post-2015 opioid crisis has greatly increased the number of organs available for donation, mostly from otherwise healthy young men like her father.

Read
Saturday, May. 30, 2026

‘Necessary active role’: corporate declaration of action adds initial signees

Gabrielle Piché 3 minute read Yesterday at 7:10 PM CDT

A model canoe took its maiden voyage Wednesday — into the arms of the National Centre for Truth and Reconciliation’s executive director.

Stephanie Scott and her team received the miniature wooden canoe during a ceremony at Assiniboine Park in Winnipeg.

They also left with a freshly signed corporate declaration of action, where national companies pledged their commitment to reconciliation.

“Your commitment, your courage is so important,” Scott told a room of roughly 15 people in the Pavilion. “It is a very long journey that we’re all on.”

Scheifele’s scoring ‘drought’ ends with pair of assists in win over Avs

Mike McIntyre 4 minute read Preview

Scheifele’s scoring ‘drought’ ends with pair of assists in win over Avs

Mike McIntyre 4 minute read Yesterday at 10:25 PM CDT

Mark Scheifele insisted he wasn’t worried.

But make no mistake: When a prolific point producer coming off a career-best offensive season puts up zeroes in his first three games, people are going to start talking.

Is this an ominous sign, some fans wondered? Is Father Time starting to catch up, others pondered?

Let the record show the so-called drought officially ended on Wednesday night in a big way when Scheifele assisted on Cole Perfetti’s second-period goal, then set up Kyle Connor’s dramatic game-winner with 60 seconds left in regulation.

Read
Yesterday at 10:25 PM CDT

A timeline of the Keystone XL pipeline

The Canadian Press 6 minute read Monday, Jan. 18, 2021

July 2008: TC Energy Corp. — then called TransCanada Corp. — and ConocoPhillips, joint owners of the Keystone Pipeline, propose a major extension to the network. The expansion, dubbed Keystone XL, would carry hundreds of thousands of barrels of oilsands bitumen from Alberta to Texas.

2009: As the U.S. State Department wades through comments based on an environmental assessment of the project, TransCanada starts visiting landowners potentially affected by the pipeline. Opposition emerges in Nebraska.

June 2009: TransCanada announces it will buy ConocoPhillips's stake in Keystone.

March 2010: The National Energy Board approves TransCanada’s application for Keystone XL, though the OK comes with 22 conditions regarding safety, environmental protection and landowner rights.

Roundup of Olympic gold medals from Tuesday, Feb. 8

The Associated Press 5 minute read Preview

Roundup of Olympic gold medals from Tuesday, Feb. 8

The Associated Press 5 minute read Tuesday, Feb. 8, 2022

BEIJING (AP) — A roundup of gold medals from Tuesday, Feb. 8, at the Beijing Games:

___

ALPINE SKIING

MEN'S SUPER-G

Read
Tuesday, Feb. 8, 2022